Checks should be made of the anchorage system at least once in every 12 months for wear, rips or chafing. Check the structure from wear or rips in the fabric, particularly in the main bouncing surface, between the walls and towers, and the surface of the step / front apron. Check that the walls and towers, when fitted, are firm and upright when inflated and that the pressure in the bouncing area/ step/front apron is sufficient to give a reliable and firm footing.
If possible, an inspection of the internal ties should be carried out from inside the structure. They should be checked for wears and tears, particularly at their loose or exposed ends. Checks of the securing of bed seams and wall to bed seams from inside should also be made.
We recommend that an annual inspection is carried out by a qualified RPII inspector.
Inflation fan
Check inlet and outlet guards and electrical connections of fan unit and ensure that each fan is PAT tested every 12 months.

|